Sarens Buildwell has completed the transport and offloading of 24 rolling stock units — three eight-coach train sets measuring 25 metres long per unit and weighing between 60 to 150 tons — at Apapa Port’s ENL Terminal
The project was completed on behalf of China Civil Engineering Construction Corporation (CCECC Nigeria) for Lagos’ Red Line railway project.
The operation required 16 axle lines of SPMTs (Self-Propelled Modular Transporters), 16 axle lines of heavy modular trailers (HMT) with a Mercedes 4060 prime mover, and two mobile cranes (230t and 500t) to move the units 500 metres from the quayside and position them directly onto the railway tracks.
The new rolling stock is expected to enter passenger service before the end of the year, expanding capacity along the Oyingbo-Agbado corridor.
Daniel Srour, deputy general manager of Sarens Buildwell Nigeria highlighted the complexity of the heavy lift project.
“Executing 24 consecutive heavy movements inside an active, congested port environment required constant coordination and strict adherence to safety protocols,” said Srour.
“Working around parked trailers, tight terminal corners and third-party vessels offloading schedules tested our team’s agility, while closed alignment with CCECC engineers ensured a smooth placement onto the rails.”
Srour said completing the operation with zero accidents “has already opened the doors to new projects with CCECC across the country.”
Sarens, a world leader in heavy lifting, engineered transport and crane rental services, is no stranger to complex logistics assignments.In this project, each unit measured 25 metres long, 3 metres wide, and 4.5 metres high with individual weights of 65 tons per coach and 150 tons per locomotive.
Sarens Buildwell was responsible for receiving the cargo under hook at the quayside, transporting each unit 500 metres across the terminal to a designated offloading area, and placing them directly onto the railway tracks.
The works were executed between November 9th and 16th, preceded by a one-day mobilisation to ENL Terminal and followed by a one-day demobilization back to Sarens’ local yard.
For the local horizon transport phase, Sarens deployed 16 axle lines of SPMTs alongside 16 axle lines of HMTs paired with a Mercedes 4060 prime mover.
Once the units reached the offloading area, Sarens utilised two mobile cranes — an XCMG XCA 230 C (230-ton capacity) and a XCMG XCA 500L8-1 (500-ton capacity) — equipped with spreader bars to lift and position the coaches and locomotives safely onto the rails.
All equipment for the project was mobilised directly from Sarens’ local Nigerian fleet.Scheduled to enter passenger service before the end of the year, each of the three new eight-coach train sets can carry up to 2,000 passengers per trip.
Once operational along the Oyingbo-Agbado corridor, the new fleet will enable more frequent services, increase commuter capacity, and provide a faster, more efficient transit option across Lagos, while helping alleviate severe road traffic congestion.